Template Hub Template Hub

Sales Cloud Template for Renewable Energy Developers

Renewable energy developers require precise tracking of land parcels, interconnection queues, and power purchase agreements (PPAs). This interactive template centralizes your pipeline from greenfield origination to commercial operation. Manage utility-scale solar, wind, and storage portfolios with a unified toolset.
✨ Get this free template installed in Salesforce in one day.
Book a free one-hour onboarding session to get started.
◄ Back to Leads List
L
Lead

Robert Vance - Vance Farms

New
Contacted
Site Evaluation
Interconnection Filed
Converted
Details
Notes
Files

Primary Information

NameRobert Vance✎
CompanyVance Farms✎
TitleLandowner✎
Lead StatusSite Evaluation✎
Target TechSolar PV✎
Lead SourceDirect Mail Campaign✎
Lead OwnerAlex Chen✎
Phone555-0199✎
Est. Project Size (MW)100✎
ISO/RTO RegionPJM✎
StateOH✎

Site & Developer Details

Parcel Acreage850✎
Interconnection Proximity1.2 miles✎
TopographyFlat/Cleared✎
Environmental Red FlagsNone Known✎
Site Control StatusEvaluating LOI✎
Substation NameScioto River Sub✎
Target Off-TakerCorporate PPA✎
Est. Yield (MWh/yr)175,000✎
Zoning StatusAgricultural (AG-1)✎
Prevailing Wage ReqYes (IRA Compliance)✎
Site GIS Review
Engineering confirmed the 850 acres are mostly clear of floodplains. The 138kV transmission line runs just north of the property line. High viability for a 100MW array.
Created by Alex Chen • Aug 01, 2026
LOI Sent
Emailed the initial Letter of Intent for an option-to-lease agreement at $1,200/acre. He is reviewing with his family trust attorney.
Created by Alex Chen • Jul 28, 2026
Inbound Response
Robert responded to the Q3 Landowner mailer. He wants to diversify farm income after a bad crop yield last year. Very motivated.
Created by System • Jul 25, 2026
◄ Back to Accounts List
Account

Midwest Power Authority

Details
Contacts
Opportunities
Projects
Interconnections
Land Parcels
Notes
Files

Account Profile

Account NameMidwest Power Authority✎
Account TypeUtility / Co-op✎
Industry SectorEnergy & Utilities✎
Websitemidwestpower.example.com✎
Account OwnerJessica Vance✎
Phone555-4422✎
Billing StateIL✎
Market Region (ISO)MISO✎

Portfolio & Financials

Total Operating MW4,500✎
Total Pipeline MW1,250✎
Primary Technology FocusSolar + Storage✎
Credit RatingA-✎
Utility PartnerN/A (Self)✎
Strategic ESG Goal80% Renewable by 2030✎
Build-Transfer Discussion
Met with Sarah Jenkins. They have capital to deploy and are looking to rate-base assets rather than just sign PPAs. We should pivot our strategy on the Springfield Solar project to a Build-Transfer Agreement (BTA).
Created by Jessica Vance • Jul 15, 2026
MISO Queue Delay Impact
The MISO DPP Phase II study for Decatur Storage was delayed 3 months. Sarah requested an updated project schedule showing how we plan to maintain the Q4 2027 COD.
Created by Robert Lin • Jun 28, 2026
Credit Rating Upgrade
S&P upgraded Midwest Power to A-. This lowers our required credit support for the upcoming PPA negotiations.
Created by Finance Team • May 10, 2026
◄ Back to Contacts List
C
Contact

Sarah Jenkins

Details
Notes
Files

Contact Information

Contact NameSarah Jenkins✎
TitleVP of Energy Procurement✎
Contact OwnerJessica Vance✎
Phone (Desk)555-4423✎
Mobile (24/7)555-9005✎
Project RoleEconomic Buyer✎

Engagement & Influence

DepartmentOrigination / Offtake✎
Influence LevelVery High✎
Preferred Contact MethodEmail✎
Technology ExpertisePPA Structuring & Finance✎
Key Decision MakerYes✎
Do Not CallNo✎
IRP Mandate Priority
Sarah emphasized that their latest Integrated Resource Plan (IRP) requires adding 500MW of dispatchable capacity. They strongly prefer BESS and Gas Peaker assets over standalone solar for this cycle.
Created by Jessica Vance • Jul 15, 2026
PPA Pricing Feedback
Received feedback on the Prairie Wind PPA. She stated our proposed $32/MWh is uncompetitive given the recent PTC extensions. We need to sharpen our pencil or pivot to a Build-Transfer.
Created by Jessica Vance • Jun 10, 2026
◄ Back to Opportunities List
O
Opportunity

100MW Solar PPA - Vance Tract

Discovery
Proposal
Negotiation
Closed
Details
Line Items
Notes
Files

Opportunity Details

Opportunity Name100MW Solar PPA - Vance Tract✎
Opportunity TypePPA Origination✎
StageProposal✎
Proposed Capacity (MW)100✎
Target ISO/RTOPJM✎
Opportunity OwnerJessica Vance✎
Close DateNov 15, 2026✎
Probability (%)50%✎
Est. PPA Revenue (Total)$35,000,000✎
Target COD (Com. Ops Date)Dec 31, 2028✎
Generation TechSolar PV✎

Commercial & Development

PPA Rate ($/MWh)$31.50✎
Escalator (%)1.5%✎
Term Length (Yrs)15✎
Delivery NodeAEP-DAYTON Hub✎
Interconnection PhaseSystem Impact Study✎
Environmental StudiesPhase 1 Clear✎
Est. Capital Cost (CAPEX)$85,000,000✎
Projected IRR (%)8.2%✎
Credit RequirementInvestment Grade Buyer✎
EPC StatusRFP Issued✎
ITC/PTC Strategy30% ITC Base✎
Next StepSubmit Final PPA Term Sheet✎
Pricing Update
Midwest Power pushed back on the $32/MWh. We revised the model assuming a 30% ITC rather than PTC, dropping the PPA price to $31.50/MWh. Awaiting their response to the revised term sheet.
Created by Jessica Vance • Aug 01, 2026
Interconnection Risk
PJM delayed the SIS results by another 2 months. We added a force majeure caveat to the COD guarantees in the PPA draft to protect against further ISO queue delays.
Created by Jessica Vance • Jul 15, 2026
Initial Proposal Sent
Submitted the initial 100MW solar proposal into their RFP portal. Offered 15-year terms. Bundled RECs included.
Created by Jessica Vance • Jun 10, 2026
◄ Back to Campaigns List
C
Campaign

Q3 Landowner Mailer - Solar

Details
Campaign Members
Notes
Files

Campaign Information

Campaign NameQ3 Landowner Mailer - Solar✎
StatusIn Progress✎
TypeDirect Mail✎
Focus AreaGreenfield Origination✎
Campaign OwnerMarketing Team✎
Start DateJul 01, 2026✎
End DateSep 30, 2026✎
Region FocusPJM Interconnection✎

Metrics & Tracking

Budgeted Cost$15,000✎
Actual Cost$12,500✎
Target Audience ProfileFarmers > 150 Acres✎
Num Sent2,500✎
Responses42✎
Opportunities Created6✎
Response Rate Tracking
We are seeing a 1.6% response rate which is fantastic for cold direct mail. The "Harvest the Sun" messaging is resonating well with generational farmers in Ohio. Distributing hot leads to the land acquisition team daily.
Created by Marketing Team • Jul 25, 2026
List Filtration
Filtered the county tax records to exclude any parcels with less than 150 contiguous acres or located more than 3 miles from a 69kV+ transmission line.
Created by Marketing Team • Jun 15, 2026
◄ Back to Projects
P
Project Asset

Vance Tract Solar 100MW

Origination
Development
Pre-Construction (NTP)
Under Construction
Operating
Details
Notes
Files

Project Identity

Project NameVance Tract Solar 100MW✎
Parent AccountMidwest Power Authority✎
Technology TypeSolar PV✎
Operating StatusDevelopment✎
Capacity (MW AC)100✎
Substation / POI NameScioto River Sub✎
Project OwnerJessica Vance✎
Commercial Ops Date (COD)Dec 31, 2028 (Target)✎
ISO/RTOPJM✎
StateOH✎
Tracking System TypeSingle-Axis Tracker✎
Panel/Turbine OEMFirst Solar (Proposed)✎

Technical & Compliance

Inverter/BESS OEMSMA (Proposed)✎
O&M ProviderTBD✎
Est. Annual Gen (MWh)175,000 (P50)✎
EPC ContractorTBD (Bidding)✎
Environmental ConstraintsNone Known✎
Interconnection QueuePJM-AF2-140✎
Permitting AuthorityOhio Power Siting Board (OPSB)✎
Tax Equity PartnerPending Selection✎
Decommissioning BondNot Funded (Pre-NTP)✎
NERC TierMedium Impact✎
OPSB Permitting Kickoff
Met with external counsel. Since the array is >50MW, we must file a full certificate application with the Ohio Power Siting Board. Pre-application notice to be sent next month.
Created by Dev Team • Aug 01, 2026
BESS Hybrid Addition
Midwest Power asked if we can add a 20MW / 80MWh battery to this project. We need to submit a modification request to PJM to see if it triggers a material modification.
Created by Jessica Vance • Jul 20, 2026
Project Originated
Project record created upon sending the draft LOI to the landowner. Moving to active development pipeline tracking.
Created by System • Jul 28, 2026
◄ Back to Interconnections
I
Interconnection

PJM-AF2-140

Application Filed
Feasibility Study
System Impact Study
Facilities Study
LGIA Executed
Details
Notes
Files

Interconnection Application

Queue IDPJM-AF2-140✎
Related ProjectVance Tract Solar 100MW✎
StatusActive✎
Utility TerritoryAEP Ohio✎
Voltage (kV)138✎
Study PhaseSystem Impact Study✎
Interconnection OwnerGrid Team✎
Application DateJan 10, 2025✎
Queue Position NumAF2-140✎
Max Injection (MW)100✎
Point of Interconnection (POI)Scioto River Sub 138kV Bus✎
Transmission ProviderPJM✎

Studies & Upgrades

Feasibility Study StatusCompleted✎
System Impact Study StatusIn Progress✎
Facilities Study StatusNot Started✎
LGIA Execution DateTBD✎
Interconnection TypeCapacity Resource (Capacity)✎
Est. Network Upgrade Cost$4,500,000✎
Contingent FacilitiesNone identified yet✎
Security Deposit Paid$200,000 (D3 Deposit)✎
Affected System StudyRequired (Duke Energy)✎
COD Extension ReqNo✎
Material Modification Request
Submitted the Mat Mod request to PJM to add 20MW of BESS to the queue. PJM has 30 days to determine if it requires a restudy. We asserted that it will charge purely from the solar and not exceed the 100MW injection limit.
Created by Grid Team • Jul 22, 2026
Affected System Study Notice
PJM notified us that Duke Energy is an affected system due to their nearby 138kV line. Duke will conduct their own study concurrent with the Phase 1 SIS.
Created by Grid Team • Jun 15, 2026
Feasibility Results
Feas study came back clean. The Scioto River Sub has a spare bay for our 138kV breaker. Direct assign upgrade costs look very manageable (~$4.5M).
Created by Grid Team • Mar 01, 2026
◄ Back to Land Parcels
L
Land Parcel

APN-998822-1

Prospecting
Evaluating LOI
Option Signed
Lease Executed
Owned / Exercised
Details
Notes
Files

Parcel Identity

Parcel NameAPN-998822-1 (Vance Main Tract)✎
APN (Assessor Parcel Num)998822-1✎
Related ProjectVance Tract Solar 100MW✎
Primary LandownerRobert Vance✎
Parcel StatusEvaluating LOI✎
CountyScioto✎
Parcel OwnerAlex Chen (Land Team)✎
Total Acreage850✎
Usable Acreage (Build Area)790✎
StateOH✎
Latitude38.7314✎
Longitude-82.9902✎

Control & Zoning

Site Control TypeLease Option (Proposed)✎
Lease Term (Years)35 (Proposed)✎
Lease Rate ($/Acre/Yr)$1,200✎
Option Expiration DateN/A✎
Zoning DesignationAgricultural (AG-1)✎
Mineral Rights StatusSevered (Third Party)✎
Phase I ESA StatusPending NTP✎
Title CommitmentOrdered✎
Easement RequiredYes - Gen-Tie Route✎
ALTA Survey StatusNot Started✎
Mineral Rights Issue
Initial public records search shows the mineral rights were severed in 1982. We will need our title team to track down the current owners and negotiate a surface waiver or drill-site accommodation agreement.
Created by Real Estate Legal • Aug 01, 2026
Title Ordered
Ordered preliminary title commitment from First American. Expected back in 14 days.
Created by Alex Chen • Jul 29, 2026
Usable Acreage Calculation
The GIS team removed the 60 acres containing the floodway and wetlands from the buildable area. That leaves us with 790 usable acres, which is more than enough for a 100MW layout.
Created by Engineering • Jul 28, 2026